Project Star Update: 

• TCO achieved
• Owner Training Held This Week.
• I 44 Off Ramp Improvements Nearing Completion.
• Landscaping and Irrigation Approximately 95% Complete.
•Traffic Signal Pole Installation Underway, Lights to follow next week.
• Metal Canopies to be installed Week of 8/12.
• Punch List has been issued and TCC is working through it.
• Steel modification Complete is shafts A&C for added breakrooms, Concrete Poured and Framing Underway.
• Shaft B Steel Demolition Underway for added breakrooms.
• MHE Control Panels ready for Testing.

 

The final touches are being put into this city changing project! Once again, MAC is honored to have had the opportunity to be a player in this incredible process!