Project Star Update: Construction is moving quickly and now into its 5th month. The Building pad is currently 95% complete, Earthwork & Grading is 95% complete, and Site Utilities are 35% installed. We have steel in the air, and the rough grading, including approximately 350,000 cubic-yards of excavation, is nearly complete. Paving began in the later part of August, and over 5% of the site paving is now on the ground. The 2.6 million square-foot facility is quickly taking shape. MAC is proud to be a part of this iconic project in Oklahoma City. See recent photos below.