Project Star Update: Despite the recent rain streak, construction is moving quickly into its 5th month. The building pad is currently 95% complete, earthwork and grading is 98% complete, and site utilities are 45% installed, with over 2,500 linear-feet of underground storm pipe already in the ground. We have steel in the air (over 20% complete) and approximately 350,000 cubic-yards of excavation is complete. Paving began in the later part of August and over 10% of the site paving is now on the ground. The 2.6 million square-foot facility is quickly taking shape. MAC is proud to be a part of this iconic project in Oklahoma City.