Project Star Update: The rains continued, but so did construction, which is now approaching its 6th month. The building pad is complete, earthwork and grading is 98% complete, and in total, over 350,000 cubic-yards of excavation is complete.Site utilities are 45% installed with over 2,500 linear-feet of underground storm pipe already in the ground, and detention pond outlet structures under construction. We have steel in the air (now over 25% complete) and concrete mezzanines and tilt panels are being installed. Paving began in late August and over 10% of the 142,407 square yards site paving has been placed. The 2.6 million square-foot facility is quickly taking shape. MAC is proud to be a part of this iconic project in Oklahoma City.