As construction is entering its seventh month, our Project Star is starting to take shape!

The building pad is complete along with earthwork and grading at 98% completion; and in total, over 350,000 cubic-yards of dirt has been excavated.

Site utilities are 50% installed with over 3,500 linear-feet of underground storm pipe already in the ground, and detention pond outlet structures complete.

We have steel in the air, (now over 40% complete), and concrete mezzanines and tilt panels are being installed, (10% complete).

Paving began in late August and over 10% of the 142,407 square yards site paving has been placed.

The 2.6 million square-foot facility is quickly taking shape. MAC is proud to be a part of this iconic project in Oklahoma City. Next time you’re in the vicinity of SW 89th St and Portland take a moment to take in the breathtaking construction 

#OklahomaBusiness #MACway #ProjectStar #OklahomaEngineering#BeCivil