Project Star Update: Construction is now in its 8th month, and the project is quickly becoming a landmark for Southwest Oklahoma City. The building pad is complete, earthwork and grading is now 100% complete with over 350,000 cubic-yards dirt excavated. Site utilities are 65% installed with over 4,500 linear-feet of underground storm pipe already in the ground, and detention pond outlet structures complete. We have steel in the air (now over 75% complete) and concrete mezzanines and tilt panels are being installed (50% complete). Paving began in late August and over 25% of the 142,407 square yards site paving has been placed. The 2.6 million square-foot facility is quickly taking shape. While work continues at the site, upgrades to the surrounding roads will begin; SW 89th St. Portland Ave. and the I-44/SW 89th interchange are all being improved as part of this project. MAC is proud to be a part of this iconic project in Oklahoma City. Next time you’re in the vicinity of SW 89th St and Portland take a moment to take in the construction.
 
#oklahoma #sitedesign #civilengineering