2019 is off to a great start and Project Star continues to make progress. The building pad, earthwork and grading are complete; with over 350,000 cubic-yards dirt excavated. Site utilities are 90% installed with over 5,500 linear-feet of underground storm pipe already in the ground. Detention ponds are installed, and the pond outlet structures are complete. We have steel in the air (now over 85% complete) and concrete mezzanines and tilt panels are being installed (70% complete). Paving began in late August and over 35% of the 142,407 square yards site paving has been placed. 15% of the landscape/irrigation has already been installed, and trees will be planted soon. The 2.6 million square-foot facility is quickly taking shape…. While work continues at the site, upgrades to the surrounding roads will begin; SW 89th St., Portland Ave., and the I-44/SW 89th Interchange are all being improved as part of this project. MAC is proud to be a part of this iconic project in Oklahoma City. Next time you’re in the vicinity of SW 89th St and Portland take a moment to take in the construction.
 
#SiteDesign #CivilEngineering #Oklahoma